Most production delays start with the drawing, not the factory. A drawing that is complete enough for a local joiner often leaves gaps for a factory producing several thousand kilometres away.
What the drawing must show
Room dimensions, wall-to-wall and floor-to-ceiling, plus the position of columns, beams, sockets and soil pipes. Elevations for every run, with unit widths and heights. A plan showing how units meet corners.
Appliance and sanitaryware models
Give the model number, not just the type. A built-in oven from one brand may need different housing dimensions from another. The same applies to basins, taps and hob cut-outs.
Finish references
Send a physical sample or a supplier colour code. A photograph cannot be colour matched reliably. Where a sample is not available, name the reference and accept that a close match, not an exact match, is what can be promised.
Packing and site access
Tell us whether the site can accept assembled units or only flat-pack, and whether there is a lift. This changes how the order is packed.